The 23 power generation companies I. Nigeria have raised concerns over their ability to sustain stable electricity supply, citing a deepening liquidity crisis in the power sector, with unpaid debts now surpassing N4 trillion.
The firms, under the aegis of the Association of Power Generation Companies, raised the alarm in a statement issued on Monday and signed by the Chairman of the Board of Trustees, Col. Sani Bello (retd.).

They said the debt burden and operational constraints currently facing the companies could force an imminent shutdown of power plants if urgent interventions were not implemented.
They warned that the continued non-payment for electricity generated and consumed on the national grid was pushing the Nigerian power sector towards a total collapse.
The statement, titled ‘Over N4tn unpaid invoices threaten GenCos imminent shutdown’, lamented the lack of a clear financing plan from the Federal Government, alongside worsening fiscal and operational constraints within the Nigerian Electricity Supply Industry.
They also accused the Nigerian Bulk Electricity Trading Plc and other stakeholders of neglecting GenCos in the application of the NESI’s “waterfall arrangement”, which sees other service providers receive 100 per cent of their market invoices while GenCos get as little as 9 per cent to 11 per cent of what is due.
The statement read: The Power Generation Companies (“GenCos”) are constrained to issue this press release to draw the attention of the Federal Government and key stakeholders to the need to urgently address the issue of inadequate payment for electricity generated by them and consumed on the national grid, which is currently threatening the continued operation of their power generation plants.
“Against the backdrop of the many challenges facing the power sector in Nigeria, the crises from cash liquidity are on the top burner and have reduced GenCos’ ability to continue to perform their obligations, thereby threatening to completely undermine the Electricity value chain.
“In the light of the severity of the issues highlighted above, the GenCos are requesting that immediate and expedited action be taken to prevent national security challenges that may result from the failure of the GenCos to sustain steady generation of electricity for Nigerians.”
Earlier in February, the Minister of Power, Adebayo Adelabu, disclosed that the government owes electricity generation companies and electricity distribution companies over N4 trillion in electricity subsidies.
Giving a breakdown, the minister said N2 trillion is owed to GenCos as legacy debt, while another N1.9 trillion is owed to them as part of the electricity subsidy for 2024, while DisCos are owed N450 billion for the 2024 electricity subsidy.